ENP Electro Novin ParsPower system testing & protection

Substation Equipment Testing

Routine and functional testing of transformers, circuit breakers, CTs, VTs and other primary equipment.

Primary substation equipment (transformers, breakers, CT/VTs, disconnectors, arresters and earthing) is the main asset of a substation, and each item is assessed with specific tests. The goal is not just pass or fail; it is to record baseline values so later maintenance can show trends and decisions can be made before a failure.

Power and distribution transformer tests

TestPurposePractical note
Insulation resistance and PI/DARCondition of insulation between windings and tank5 or 10 kV; record oil temperature for correction
Turns ratio (TTR)Winding and tap-changer integrityAll taps; typical tolerance ±0.5%
Winding resistance (DC)Internal connections and tap-changer contactsCompare phases and factory values
Tan δ and capacitanceMoisture and ageing of insulation, bushingsBushing test in UST mode
Excitation currentCore faults and inter-turn faultsCompare the three phases
Short-circuit impedanceMechanical deformation of windingsCompare with nameplate and previous test
SFRA (IEC 60076-18)Winding and core displacementEspecially after transport or a severe through-fault
Dissolved gas analysis (DGA)Internal faults such as arcing, hot spots, partial dischargeStandard sampling per IEC 60599
Oil tests (breakdown voltage, moisture, acidity)Insulating oil qualityBefore energization and periodically

CTs and VTs

  • Ratio and polarity by primary or secondary injection
  • Excitation curve (knee point) to confirm no saturation at fault current
  • Secondary winding resistance and burden to check accuracy class
  • Insulation resistance and single-point secondary earthing
  • For VTs: ratio, polarity, burden, fuse and secondary circuit condition

Circuit breakers and disconnectors

TestApplication
Contact resistance (micro-ohm)Main contacts; typically tens of micro-ohms
TimingOpen and close times, pole discrepancy, trip and close
Travel curveMechanism condition and stroke
Insulation and withstandPole insulation in open and closed positions
SF6 pressure and qualityLeakage, moisture and purity
Minimum coil voltage and currentOperation at 70% and 85% of rated voltage

Other equipment

  • Surge arresters: insulation resistance and leakage current; resistive tests
  • Earthing system: earth resistance (fall-of-potential, IEEE 81), touch and step voltage, conductor continuity
  • MV switchgear: insulation resistance, AC or VLF withstand, busbar contact resistance, mechanical interlocks
  • Battery and DC charger: capacity, cell voltages, discharge test, charger and DC earth-fault relay
  • Thermography: find hot spots in connections under load

Standards and reporting

Tests follow IEC 60076, IEC 62271, IEC 61869 and IEEE C57. The report includes nameplate data, ambient conditions, calibrated instruments, measured values, comparison with limits and a pass or fail result, and is kept as a reference for later maintenance.

Scope of work

  • Complete transformer testing: TTR, winding resistance, tan δ, SFRA
  • Oil sampling and DGA interpretation
  • CT/VT ratio, polarity and excitation curve tests
  • Breaker contact resistance, timing and travel curve
  • Earth resistance, touch and step voltage measurement
  • Battery, charger tests and thermography
  • Baseline reference report for later maintenance